Early and enabling works to get underway on Somerset Dam Improvement Project

Monica Gameng   |   June 29, 2024
Somerset Dam (cr: Seqwater)

The first stage of the Somerset Dam Improvement Project in Queensland is gearing towards major construction as early and enabling works commence. 

Early and enabling works include: 

  • Broad scale geotechnical investigations including installation of dam surveillance instrumentation 
  • Removal of existing spillway (radial) gates as these no longer form part of Seqwater’s operation of the dam 
  • Replacement of the sluice gates (gates at the bottom of the dam) and outlets that are reaching the end of their serviceable life 
  • Construction of a temporary coffer dam that will help to maintain a dry work site downstream when investigations and construction commences in areas currently submerged 
  • Relocation of the existing operations facilities to allow construction of the future main dam upgrade 
  • Temporary and permanent access road works including a permanent realignment of Esk-Kilcoy Road and a new access to the dam wall from Wivenhoe-Somerset Road 
  • A range of investigations, studies and assessments to support finalisation of the Detailed Business Case for the main dam upgrade 

Procurement is also underway for the manufacture of modern, purpose-built and hydraulically operated sluice gates, with tender submissions already received. Manufacturing works will start in 2025 once the contract is awarded and upon receiving project approvals. 

“While dams in Queensland were built to very high, internationally accepted safety standards, Somerset Dam was built by 1959, and dam design and engineering standards have evolved significantly since then. 

“As part of the Somerset Dam Improvement Project, Seqwater is pleased to be planning a range of early and enabling works to support future construction on the major dam upgrade planned at this site. 

“The works are required to be completed irrespective of the final design option for the Somerset Dam Improvement Project, which is currently being considered as part of the Detailed Business Case stage. 

“Subject to project approvals, the majority of the early and enabling works are expected to commence on-site in 2025, and Seqwater will continue to keep the community informed,” Seqwater Interim CEO Will Harpham said. 

Seqwater is planning to host drop-in information sessions in July and August of this year where they will be providing the community with further information about the planned works for the project. More information on the sessions will be released once confirmed. Seqwater is also encouraging community members to sign up for the project newsletter on its website. 

A Detailed Business Case for the Somerset Dam Improvement Project is already in the works, carefully assessing the preferred option for upgrading the dam. Seqwater will continue to keep the community updated as the project progresses. 

The Queensland Government has committed $13 million, through the 2024-25 State Budget, for planning works on the project. 

The Somerset Dam Improvement Project is anticipated to support up to 150 jobs. 

The proposed main dam upgrade includes: 

  • Raising the height of the dam wall to improve function during very extreme floods 
  • Extending and reinforcing the dissipator basin and training walls, plus adding a new control structure, downstream of the spillway to reduce energy from the spillway flow in very extreme weather events 
  • Adding concrete to the downstream face of the dam wall to help strengthen the wall 

“This is an important and complex project to make sure Somerset Dam continues to withstand extreme flood events into the future and provide water security for years to come. 

“Seqwater has already delivered 13 dam upgrades, and I am pleased to see works commencing on Somerset Dam soon as part of this important program of works in the region. 

“There’s going to be around 150 jobs throughout the life of the project,” Minister for Water Glenn Butcher said. 

Source: Queensland Government – Media Statements; Seqwater (1, 2

New call-to-action

Monica Gameng
As Felix's Marketing Assistant since 2015, Monica is responsible for researching and sharing new and progressing projects within the construction and mining sectors in Australia. It's no surprise that Monica has her finger on the pulse of Australian major projects given she has produced more than 1,000 posts. She truly is an industry expert.
Follow me:

Related Articles

Projects
WA Byford Rail Extension project to support over 300 local jobs

Another METRONET project is progressing well with the Request for Proposals process commencing for the Byford Rail Extension. 

Projects
Multiplex to begin works on $800m Karrinyup Shopping Centre expansion WA

Works is set to go underway on an $800 million expansion project that will almost double the size of the Karrinyup Shopping Centre in Western Australia, with AMP Capital - in behalf of UniSuper - naming Multiplex as the preferred builder for the project.

Projects, NT
Core Lithium commences early works on BP33 mine project

Core Lithium has commenced early works on the BP33 underground mine project, which is part of the expansion of its Finnis Lithium Operations in the Northern Territory. 

Get the latest project news

Formerly known as the PlantMiner blog, Felix Project News is Australia's top 10 Construction blog. Join thousands of construction and mining pros getting the best content right in their inbox.
  • updates on Australia's pipeline of state and federal projects
  • fresh contract awards from major contractors and builders

If you're looking to contact us about other matters, please contact us.